Rancho Cucamonga High School Auditorium

Home/Rancho Cucamonga High School Auditorium

RANCHO CUCAMONGA HIGH SCHOOL AUDITORIUM PROJECT PROGRESS REPORT THROUGH 6/30/17

The choral, drama and two classrooms have been turned over to the district.  Their furniture has been brought in and the teachers classrooms have been transferred.  The theater accoustical wall panels and carpet has been installed.  The theater audio, lighting and fire alarm are being tested.  The west side parking lot concrete and asphalt are complete and the fence panels and gates have been installed.  Landscaping of shrubs and trees is in progress.

  

  

  

  

  

RANCHO CUCAMONGA HIGH SCHOOL AUDITORIUM PROJECT PROGRESS REPORT THROUGH 5/31/17

The stage floor has been installed and the rigging is being finalized.  The theater chairs were installed and the sound panels are being installed.  The final audio and electrical finish is being installed in the theater. The lobby wall tile and ceiling grid are complete and the floor tile is being installed.  The east and west wings punch list has been generated and distributed to the subcontractors.  The east side sitework is complete and fence panels are installed.  The landscaper has started irrigation lines on the east.  The south side concrete is being poured and the west side final grading is complete and fence posts are being installed.

  

  

  

RANCHO CUCAMONGA HIGH SCHOOL AUDITORIUM PROJECT PROGRESS REPORT THROUGH 4/30/17

The stage rigging is installed.  The paint has been applied to the inside theater.  The sound booth has been painted and T-bar has been installed.  The equipment racks have been delivered and are being installed.  The lobby drywall is complete and the porcelin wall panels have started.  The east and west rooms have casework, fire extinguisher cabinets, and markerboards installed.  The ceiling grid is installed.  The acoustical tiles will follow the completed ceiling grid.  The metal panels are complete except the south canopy.  The stucco has been painted.  The east parking lot turn around asphalt is complete and striped.  The concrete sidewalk is begining on the east side and moving to the west.

  

  

  

RANCHO CUCAMONGA HIGH SCHOOL AUDITORIUM PROJECT PROGRESS REPORT THROUGH 3/31/17

The drywall finish and painting is complete in the theater.  The HVAC and Electrical trim is complete and the scaffolding is being removed.  The lobby drywall is hung and drywall finish is starting.  The stage is painted black and ready for riggning to begin.  The east and west sides have both been painted and the T-bar grid has been installed.  The tile in the gang restrooms has started.  The plaster scratch and brown coat are complete and the finish coat is starting  The east parking lot turn around has been graded and the curb has been poured.

  

  

  

  

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 1/31/17

The high elevation scaffolding is complete.  The trades are proceeding on overhead sprinkler rough, electrical rough in at the overhead conditions, The metal catwalk and mezzanine framing and catwalk handrails are progressing.  The Theater roof is complete pending the sheet metal cap at the perimeter.  The east side of the building roof is complete.  The Mechanical Electrical and Plumbing in-wall utilities and metal stud backing in the east and westside of the auditorium are progressing.  The north facade framing is almost complete. The east and west exterior lath is being installed.

  

 

  

  

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 11/30/16

The metal decking on the east and west classrooms is complete.  The metal decking for the theater is being installed.  Sprinkler mains in the theater have started.  Plumbing is being installed above the stage.  The stage area and restrooms slab on grade were poured.  The fine grading for the theater is complete and electrical underground is starting.  The canopy columns were set and the CMU is being built around them.  Scaffolding on the north, east and west sides of the building is erected.

lobby-columns-and-canopy  stage-stego-wrap

ticketing-booth  west-wing-steel-deck

north-facade-scaffolding artificial-turf

lobby-canopy-and-columns

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 10/31/16

The structural steel installation is complete for the theater and east and west classroom buildings.  The welding is about 90% complete.  The catwalk above the stage is complete and the underground electrical has begun.  The catwalk, mezzanine and clouds in the theater are being intalled now.  The vapor barrier and rebar is down for the stage, gang restrooms and sound booth concrete.  Metal stud framing has started in perimeter rooms.  The metal decking has been placed on the roof of the theater and outside classrooms.

theater-roof-steel  catwalk-stage

choral-room lobby-canopy

sound-booth-slurry framing-classrooms

theater-cloud theater-cloud-east

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 9/30/16

The block is complete in the theater along with the east and west classrooms.  The scaffolding has been removed for the block installation.  The Mason is completed and has demobilized from the site.  The structural steel has been received for the theather roof is in the processes of being erected and is being bolted up and welded off.  The steel is being erected in the east and west classrooms.  The plumbing underground for the public gang restrooms has been installed and backfilled.

north-stage-and-theater  southeast-crane

southeast-crane-main-beams  east-theater-roof-steel

east-stage-steel  underground-storm-drain

east-classrooms  auditorium-roof-steel

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 8/24/16

The center theather block walls are complete and scaffolding is removed.  The start of the structural steel material delivery is in progress with some of the roof steel member sent to the site this month.  The west classrooms walls are at 18′ high and the east classroom walls are at 8′ high.  The slab on grade for the east and west wings have been poured.

looking-east-choir-room  looking-west-stage

looking-south-theater  looking-south-choir

looking-norht-stage  looking-north-classroom-slab

north-entrance  east-auditorium

south-auditorium

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 7/31/16

Auditorium Block walls moving up to approximately 32′ high.  The catwalk embeds for the main Auditorium are installed and the adjoining roof embeds are installed.  The underground fire and domestic water street work is complete and lines are installed up to the building.  The new stairs in the quad are complete and poured back, ready for start of school.  Building U remodel is complete and ready to receive students.

Quad ramp  Quad Hardscape

Ramp construction  Auditorium Lobby

Auditorium Theater  Auditorium Stage

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 6/30/16

This month the auditorium block walls are up to about 16′ high.  The first row of embeds for the steel were on the mezzanine level and have been grouted.  The new utilities for the auditorium are complete and backfilled. Some of the utilities came from the fire road area and needed to be routed through the quad area.  The new concrete slab on grade for the quad has commenced.    The asphalt in the fire has been placed back.  Building U demolition is complete, the walls are framed and have first coat paint on the drywall.  T-bar wire and grid is being installed for the acoustical ceiling tile.

Portables were set and rough in for power rough in began for the portables.

Demo bldg U  quad utilities

cmu walls going up  cmu walls east

cmu walls east2  quad flatwork

ramp walls

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 5/31/16

Footings for Auditorium are complete.  Block walls for center of Auditorium are up past 4′.  The ramp walls and retaining wall north of the quad are poured.  The demolition of the quad is complete and the utilities are being installed through the quad.  Building U demolition is complete and new construction is just beginning.  New gas line through the fire road has started this month.

Footing rebar cages  CMU walls

East ramp walls  Rebar and steel columns

Retaining Wall Footing  Demolition of quad

Auditorium Lobby  Quad sewer

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 4/30/16

Building and site sewer, storm drain, water and gas underground is partially installed, west ramp footings are poured and walls are formed, site underground electrical is being installed and building footings are being dug.  Reinforcing bar is being set in the footings.  Early steel columns are in fabrication as well as hollow metal frames needed for block walls.

Storm drain and gas  footing formwork

auditorium footprint  stage wall footing

ramp wall formwork  electrical ductbank

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 3/31/16

The project demolition has begun.  The existing parking lot, concrete sidewalk and quad ADA ramps were removed.  The over excavation operation under the footings is complete and rough grade and soil export is almost complete.

Auditorium Footprint  Demo W

Quad Ramp Demo  Overexing

Crushing and seperating  Rought Grade Pad