Valley View High School Project Progress Report Through 07/31/14

Valley view shade structure is completed.

Valley View Looking South(2) 07_30_14  Valley View Looking South 07_30_14

Valley View Looking North 07_30_14  Valley View Looking East 07_30_14

Valley View High School Project Progress Report Through 06/30/14

Valley View shade structure is in progress. The footings were completed, shade structures were all erected and assembled, and the Masonry column wraps are installed. The concrete slab is prepared and the next step will be to pour the concrete slab and connect the shade structure down spouts.

Looking Southeast at Shade Structure   Shwnee Shade Structure

Valley View High School Project Progress Report Through 06/15/14

Valley View shade structure installation has started in June 2014. Currently all material for the shade structure is onsite and general layout and grading of the site have started.  Drilling for footings is in progress.

Excavation progress_060614  Material received

Reinforcing Cages

Planned Improvements

Proposed New Improvements

– New classroom building (replace portables)
– New inclement weather shelter

Proposed Renovation Improvements

– ADA accessibility upgrades
– Low maintenance flooring
– Acoustically enhanced classroom ceilings
– Energy efficient insulated windows
– Energy efficient light fixtures
– Low water use plumbing fixtures
– High efficiency air-conditioning/heating
– ‘Cool roof’ membrane surfaces
– Upgraded power distribution
– Natural day-lighting
– Modern, addressable fire alarm upgrades
– Technology Upgrades including network,
     classroom and desktop upgrades
– Increased Security Upgrades: Fencing
     and Cameras

Valley View Plan