RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 1/31/17

The high elevation scaffolding is complete.  The trades are proceeding on overhead sprinkler rough, electrical rough in at the overhead conditions, The metal catwalk and mezzanine framing and catwalk handrails are progressing.  The Theater roof is complete pending the sheet metal cap at the perimeter.  The east side of the building roof is complete.  The Mechanical Electrical and Plumbing in-wall utilities and metal stud backing in the east and westside of the auditorium are progressing.  The north facade framing is almost complete. The east and west exterior lath is being installed.

  

 

  

  

 

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 11/30/16

The metal decking on the east and west classrooms is complete.  The metal decking for the theater is being installed.  Sprinkler mains in the theater have started.  Plumbing is being installed above the stage.  The stage area and restrooms slab on grade were poured.  The fine grading for the theater is complete and electrical underground is starting.  The canopy columns were set and the CMU is being built around them.  Scaffolding on the north, east and west sides of the building is erected.

lobby-columns-and-canopy  stage-stego-wrap

ticketing-booth  west-wing-steel-deck

north-facade-scaffolding artificial-turf

lobby-canopy-and-columns

 

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 10/31/16

The structural steel installation is complete for the theater and east and west classroom buildings.  The welding is about 90% complete.  The catwalk above the stage is complete and the underground electrical has begun.  The catwalk, mezzanine and clouds in the theater are being intalled now.  The vapor barrier and rebar is down for the stage, gang restrooms and sound booth concrete.  Metal stud framing has started in perimeter rooms.  The metal decking has been placed on the roof of the theater and outside classrooms.

theater-roof-steel  catwalk-stage

choral-room lobby-canopy

sound-booth-slurry framing-classrooms

theater-cloud theater-cloud-east

 

 

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 9/30/16

The block is complete in the theater along with the east and west classrooms.  The scaffolding has been removed for the block installation.  The Mason is completed and has demobilized from the site.  The structural steel has been received for the theather roof is in the processes of being erected and is being bolted up and welded off.  The steel is being erected in the east and west classrooms.  The plumbing underground for the public gang restrooms has been installed and backfilled.

north-stage-and-theater  southeast-crane

southeast-crane-main-beams  east-theater-roof-steel

east-stage-steel  underground-storm-drain

east-classrooms  auditorium-roof-steel

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 8/24/16

The center theather block walls are complete and scaffolding is removed.  The start of the structural steel material delivery is in progress with some of the roof steel member sent to the site this month.  The west classrooms walls are at 18′ high and the east classroom walls are at 8′ high.  The slab on grade for the east and west wings have been poured.

looking-east-choir-room  looking-west-stage

looking-south-theater  looking-south-choir

looking-norht-stage  looking-north-classroom-slab

north-entrance  east-auditorium

south-auditorium

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 7/31/16

Auditorium Block walls moving up to approximately 32′ high.  The catwalk embeds for the main Auditorium are installed and the adjoining roof embeds are installed.  The underground fire and domestic water street work is complete and lines are installed up to the building.  The new stairs in the quad are complete and poured back, ready for start of school.  Building U remodel is complete and ready to receive students.

Quad ramp  Quad Hardscape

Ramp construction  Auditorium Lobby

Auditorium Theater  Auditorium Stage

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 6/30/16

This month the auditorium block walls are up to about 16′ high.  The first row of embeds for the steel were on the mezzanine level and have been grouted.  The new utilities for the auditorium are complete and backfilled. Some of the utilities came from the fire road area and needed to be routed through the quad area.  The new concrete slab on grade for the quad has commenced.    The asphalt in the fire has been placed back.  Building U demolition is complete, the walls are framed and have first coat paint on the drywall.  T-bar wire and grid is being installed for the acoustical ceiling tile.

Portables were set and rough in for power rough in began for the portables.

Demo bldg U  quad utilities

cmu walls going up  cmu walls east

cmu walls east2  quad flatwork

ramp walls

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 5/31/16

Footings for Auditorium are complete.  Block walls for center of Auditorium are up past 4′.  The ramp walls and retaining wall north of the quad are poured.  The demolition of the quad is complete and the utilities are being installed through the quad.  Building U demolition is complete and new construction is just beginning.  New gas line through the fire road has started this month.

Footing rebar cages  CMU walls

East ramp walls  Rebar and steel columns

Retaining Wall Footing  Demolition of quad

Auditorium Lobby  Quad sewer

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 4/30/16

Building and site sewer, storm drain, water and gas underground is partially installed, west ramp footings are poured and walls are formed, site underground electrical is being installed and building footings are being dug.  Reinforcing bar is being set in the footings.  Early steel columns are in fabrication as well as hollow metal frames needed for block walls.

Storm drain and gas  footing formwork

auditorium footprint  stage wall footing

ramp wall formwork  electrical ductbank

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 3/31/16

The project demolition has begun.  The existing parking lot, concrete sidewalk and quad ADA ramps were removed.  The over excavation operation under the footings is complete and rough grade and soil export is almost complete.

Auditorium Footprint  Demo W

Quad Ramp Demo  Overexing

Crushing and seperating  Rought Grade Pad

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 2/29/16

 

 

The remaining handrail and guardrail are being installed at the stairs and ramps.  The project team is working through a few remaining punchlist items.  The City landscaping at Victoria Park Ln is being installed.

Basketball Courts  Varsity Softball

JV baseball and bleachers  Stadium SW

Varsity BB SE  Tennis Court Restriping

South Parking Lot

 

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 1/31/16

The stairs from the new parking lot to the stadium plaza were completed this month.  The new parking lot was striped.  The remaining handrail and guardrail are in progress at the stairs and ramps.  The landscaping around the parking lot is in the final stages.

SE Entrance  se exit and landscaping

parking lot striping  SE stadium ramp

Tennis court  south parking lot

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 11/30/15

The epoxy flooring in the concession building is complete.  The concession equipment is complete.  The toilet partitions and plumbing finishes are complete in the conession.  The HVAC units have been turned on.  The last ramp wall at the SE corner of the stadium is being constructed.  The remaining curbs in the parking lot are being  formed and poured.  The drive approach at Victoria has been poured.  Fire Alarm, Security and Data wire is pulled and being tested.

sidewalk of tennis court  concession ticketing booth

east side of concession  east palm trees

south victoria park lane  north inside concession

south inside concession bathroom  jv baseball and softball

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 10/31/15

The track surfacing is complete and striped.  Building Y T-bar is installed and fixtures are complete.  The existing bleacher have the brackets installed for the new benches.  The exterior concrete around the concession building is poured.  The painting is complete in the conession building.  The tile work is progress in the concession restrooms.  The metal panels are complete on the exterior.  All MEP ceiling trim is currently being installed.  The concession building wire is being pulled.  The solar is complete  in the parking lot crubs can begin.

retaining wall  east d zone

bleacher and track  concrete ramp footing

track and field  track and field ne

bb and solar panels

RANCHO CUCAMONGA HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 9/30/15

The south bleacher and press box is complete.  The concession building drywall is currently being hung and taping has started.  The concession roofing is complete and coping is being installed.  The HVAC units have been installed and electrical is being hooked up.  Building is currently being painted and roofing and HVAC units are complete.  All retaining walls along the fire road are complete and flat work on the ramps is being poured.  The flatwork on the east side of the concession is complete.  The track surfacing has started.  The synthetic turf is complete.   The offsite work on Victoria Park Ln. is underway with rough grade and forming of curbs.

Present:

  • Installing flatwork east side of concession.
  • Installing tile in concession restrooms.
  • Taping and sanding walls concession.
  • Hanging T-bar in building Y.
  • Pouring footings for Marquee sign.
  • Hanging tube steel fencing.
  • Installing track surfacing.

Future:

  • Hanging doors concession.
  • Painting Interior & Exterior concession.
  • Hanging Toilet Partitions.
  • Pouring Tennis Court Ramp.
  • Pouring Footings for Basketball Court.

Concession Building NW  South bleacher and tuf

North concession plaster and track  west pouring concrete ramp

South victoria park  flag pole installation

Northeast pouring steps  South installation of track surfacing

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 8/31/15

The bleacher steel is complete and aluminum planking is being installed.  The concession building framing is almost complete and all utilities are being roughed in.  The concession roofing is being installed and exterior plaster system is being installed.  Building Y framing is complete and utilities are being roughed in.  New roof for building Y is beginning.  The last retaining walls along the fire road will be completed. Demolition of the offsite drive approach is beginning. The synthetic turf will be completed by the end of the month.

Commisioning Musco Poles  southeast turf

bleacher and pressbox

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 7/31/15

The track has been fully paved.  The bleacher footings have poured and undernearth flatwork is being placed.  The synthetic turf substrate is complete and ready to install turf.  Remaining retaining walls are being worked on.  The stadium lighting musco poles have been installed.  The concession building metal decking has been installed and framing has begun along with plumbing piping.  The building Y roof has been removed and the new structural steel holes have been cut open.

Musco Pole W  Field Drainage SE

NW Musco Pole  Formwork for Bleacher S

Track Asphalt  Track Asphalt W

Field Base SW  Finished Bleacher footings

 

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 6/30/15

All irrigation and sod has been installed in all 4 fields.  Flatwork at the playfields is complete.  All scoreboards have been installed.  All fencing and gates have been installed in the playfields.  Structural steel and decking are almost complete at concession.  Waste and vent piping has started.   Track curb, drainage and grading has started.  Bleacher footings have started.  Elevator has been installed.   Demolition of Y building has begun.  Flatwork on the upper field has started and the upper field retaining walls are also underway.

Concession Building East  Bleacher elevator sw

Varsity SB ramp S  Concession building W

 

Varsity BB sod SW  electrical infrastructure E

varsity SB scoreboard

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 5/31/15

The underground gas and water line were installed to the concession building.  The playfield concrete flatwork is progressing.  The foul ball poles have been installed for the playfields and the chain link fencing is progressing.  The irrigation and soil preparation of for the JV and Varsity Softball fields was completed and the sod was installed in these two fields. The backstop boards were installed in the fields.  Fine grading for the parking lot and track and field started.  The field cooling for the synthetic field was completed.  The roofing for the storage building was completed and the metal stud framing, drywall and plaster was completed.  The doors are hung and paint of the interior and exterior is taking place.  The concession building CMU walls almost topped out.  The demolition of building Y has started.  The elevator pit and machine room slab have been poured.  The elevator has been placed.

Varsity softball irrigation  Field cooling

Fine grading varsity field  ticket booth cmu

Varsity softball sod installation  electrical infrastructure

completed sod  playfield ramp footings

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 4/30/15

The block walls for the storage building are complete and the structural steel/metal decking has been installed. The block walls for the concession building are is in progress and the slabs inside the concession are progressing through the structure. The concrete flatwork outside the storage building has been poured. The backstop post and chainlink fencing has been installed for all 4 fields. Perimeter chainlink fencing has been installed on the south and west property lines.  The irrigation main line is complete in the playfields. The dugout posts have started to be placed. The water lines, electrical infrastructure and storm drain systems for the playfields are all complete.  The onsite soil is currently being sifted to remove rocks out of the dirt to create a suitable topsoil to lay sod.

south storm chamber  Storage Bldg

sewer connect bldg y  Ramp wall excavation

south jv softball  storage building slab

CMU at concession  Rock sifting

 

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 3/31/15

The concrete contractor is continuing to form and pour the retaining walls onsite.  The underground utilities in the playfields and near the concession building are being installed.  The backstop posts in the playfields began along with the perimeter fencing and playfield chain-link fencing.  The storage building footings were poured and the block has started.  The concession building underground plumbing was installed and the footings were excavated and rebar was installed.  Demolition of the existing bleacher for the Musco poles and new ADA seating is completed.  new parking lot started this month.

retaining wall west  electrical conduit

footing rebar  retaining wall excavation

concession bldg plumbing  footing poured

storm tech  lateral irrigation

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 2/28/15

The grading and demolition contractor completed the rough grading of the baseball fields and stadium. The bio swales in the baseball and softball fields were completed. The electrical infrastructure in the fire road was completed and asphalt was put back on the road. The electrical infrastructure for the new stadium began. Demolition of the existing concrete bleachers for the new ADA seating and new Musco stadium lighting began. The concrete contractor mobilized onsite and began the new retaining wall footing excavations, footing rebar and wall formwork for the wall that splits the upper and lower field. The plumbing contractor installed and backfilled the new sewer main line along the new concession building and began installation of the 18” main Storm Drain line that will travel to the parking lot from the stadium field.

S Bio Swale Varsity BB  Electrical Conduit Fire Lane

East Excavation  East Retaining Wall Footing

Over Excavation  South Pour Retaining Wall

 

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 1/31/15

The grading and demolition contractor completed demolition of the old fields, stadium and basketball courts. Rough grading began on the fields and track areas. Over excavation of the soil under the retaining walls and new buildings began. Installation of the new electrical infrastructure began in the fire access road.

Scarify Topsoil Playfields East  West Demo of Field

South Rough Grading  East Over Excavation

West Excavation of Fire Road  West Excavation of Fire Road behind stadium

Rock Trench  Storm Drain Rock

Electrical Conduit

 Groundbreaking 17, 2015

IMG_1888  IMG_1883

IMG_1896  IMG_1885

IMG_1884

RANCHO CUCAMONGA HIGH SCHOOL ATHLETIC FIELDS IMPROVEMENTS PROJECT PROGRESS REPORT THROUGH 12/31/14

The grading and demolition contractor mobilized this month and began by building the construction entrance. The temporary construction fencing was installed at the perimeter of the construction site. The grass was stripped from the athletic fields and hauled off. Demolition was completed at the basketball courts, Track & Field, behind the weight room, sport field fencing, pitcher mounds, and dugouts. Demolition of the existing stadiums began on the east and west of the existing bleachers.

Temp fence  Striping Existing Grass

Basketball demo  Demo Basketball north

Demo Track and Field