ONTARIO HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 02/29/16

Buildings:  Finalizing the added wall tile at girl’s restrooms.

Stadium: Working on additional fencing barrier at ADA walkway near JV Softball field.

Fields: New underground retention basins are installed.  New V-Gutter was installed.

First Home Game  Class Picture

ONTARIO HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 01/31/16

Synthetic turf installation is complete.  Stadium A/V is complete. Site landscaping is complete.  Synthetic track surfacing installation is ongoing.

North Stadium east  North stadium east2

Podium  Dedication

East track

ONTARIO HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 12/31/15

Stadium Buildings:  Electrical finishes are complete.  Classroom flooring is complete.  Exterior painting is ongoing.

Stadium: Site gates installation is ongoing.  Synthetic turf installation is ongoing.  Site irrigation is complete.  Site final landscaping has begun.

Entry Gates North  Stadium East

East Field Drainage  Stadium East2

North stadium east  North stadium east2

Cypress drainage

ONTARIO HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 11/30/15

Buildings:   Toilet partitions and accessories are complete.  Plumbing finishes are complete.  Electrical finishes are ongoing.  Fire Alarm & Intrusion Alarm is ongoing.  Exterior anti-graffiti coatings are complete.  Pass through countertop windows & roll up doors are complete.  Kitchen equipment is installed.  Classroom flooring is ongoing.

Stadium: Base and asphalt for the Track & D-Zones is complete. Flatwork around buildings is ongoing.  New storm drain line pump station is installed.  Offsite storm drain and driveways are complete.  Site hollow metal gate installation is ongoing.

Aquatics Center: Solar Piping is on hold for redesign of structural support.

Cypress street  Stadium entry norht

North stadium  South track base

Health classroom  Track paving

ONTARIO HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 10/31/15

Buildings:  Toilet partitions and accessories are ongoing.  Plumbing and electrical finishes are ongoing.  Exterior anti-graffiti coatings are ongoing.  Pass through countertops are complete.  Ceramic tiles at restrooms is complete.  Epoxy flooring in kitchen is complete.  Kitchen equipment has been delivereStadium: Site fencing is ongoing.  Fine grading for stadium track/field is complete.  Outside track curb is complete, inside curb is ongoing. Planting at north slope is complete.  Flatwork around buildings is ongoing.  New storm drain line is complete across stadium.  Offsite storm drain work is ongoing.

canopy steel  stadium south

south storm drain  canopy steel south

concession flooring  Staff restrooms

North slope  Building L restroom

concessions kitchen  offsite work

track curbs  anti graffiti and scoreboard

offsite at Francis