MONTCLAIR HIGH SCHOOL HVAC UPGRADES PROJECT PROGRESS REPORT THROUGH 9/30/15

The project consist of the removal of the heating units at buildings “B” and “C” and providing new

HVAC units at building “B” and “C” and associated new steel beams at buildings “B” and “C” to support new HVAC units.  The project started on May 22, 2015 upon completion of school.  The demolition at the exterior and interior is complete.  The project has new ductwork and HVAC unit in place for the area serving the staff lunch area in C.

The project has completed the scope and is continuing with commissioning  the units and punchlist

AHU Hook up Roof patches

MONTCLAIR HIGH SCHOOL HVAC UPGRADES PROJECT PROGRESS REPORT THROUGH 8/31/15

This month’s focus was on Bldg B, Auditorium.  Completed the support steel for the new roof penetrations and replaced the decking.  The roof was completed for the Building C this month.   Building B the steel supports were installed and the roofing decking replacement is in progress.  The new electrical feed for the units’ progresses and the gas is complete pending the new unit connections.

tube steel support  deck support

AC unit being lifted

MONTCLAIR HIGH SCHOOL POOL PROJECT PROGRESS REPORT THROUGH 8/31/15

The pool was turned over to the site on 8/26/15 for use.

Pool west  Fire Lane South

South walkway  Pool heaters

south walkway west  Pool East

MONTCLAIR HIGH SCHOOL HVAC UPGRADES PROJECT PROGRESS REPORT THROUGH 7/31/15

The project consist of the removal of the heating units at buildings “B” and “C” and providing new

HVAC units at building “B” and “C” and associated new steel beams at buildings “B” and “C” to support new HVAC units.  The project started on May 22, 2015 upon completion of school.  The demolition at the exterior and interior is complete.  The project has new ductwork and HVAC unit in place for the area serving the staff lunch area in C.

This month’s focus was on Bldg C, Cafeteria.  Completed the support steel for the new roof penetrations and replaced the decking.  The roof was completed for the Building C this month.   Building B the steel supports were installed and the roofing decking replacement is in progress.  The new electrical feed for the units’ progresses and the gas is complete pending the new unit connections.

conduit Bldg B  Conduit backfill

Ductwork Bldg C  Structural Steel Bldg C

Roof patches Bldg C  Dining area upgrades Bldg C

MONTCLAIR HIGH SCHOOL PROJECT PROGRESS THROUGH 7/31/15

Pool deck concrete is complete.   Pool plaster is complete & pool is filled.  All site concrete walls are complete.  ADA ramp concrete is complete.  Pool gutter is complete.  Fence panels are complete.  Cafeteria re-roofing is complete.  Pool mechanical equipment is ongoing.  Fire alarm work is ongoing.  Outdoor shower work is ongoing.  Pool solar piping system is ongoing.  Deck tile work is ongoing.  Bleacher handrail work is ongoing.

Sourth Ramp Walls N  Pool Looking NW

1st Pool Deck E  2nd pool deck W

Pool Railings N  Locker Room Walkway W

Pool Plaster S

MONTCLAIR HIGH SCHOOL HVAC UPGRADES PROJECT PROGRESS REPORT THROUGH 6/30/15

The project consist of the removal of the heating units at buildings “B” and “C” and providing new

HVAC units at building “B” and “C” and associated new steel beams at buildings “B” and “C” to support new HVAC units.  The project started on May 22, 2015 upon completion of school.  The demolition at the exterior and interior is complete.  The project has new ductwork and HVAC unit in place for the area serving the staff lunch area in C.  The associated ductwork for the unit is in progress.   Building B has ductwork in progress and new gas line to feed the new unit is complete and the roof is open for the location of the new units for field measuring of steel for new supports.

Buildling C ductwork  Building C roof demo

Building B gas line  building B ductwork

MONTCLAIR HIGH SCHOOL PROJECT PROGRESS THROUGH 6/30/15

The project consists of the demolition and replacement of the swimming pool and associated pool equipment.  New bleacher seating is also being added to the pool equipment building.

Pool deck is graded.   East retaining wall is complete.  West bleacher extension wall is poured.  Stair & ADA ramp footings are complete.  Building concrete slabs are poured.  Doors are installed at the new equipment rooms.  Underground pool deck slot drain is ongoing.  Gutter framing is ongoing.  South fence posts are installed.  Cafeteria re-roofing is ongoing.

Pool Storm Drain west  New Equip rooms east

East retaining wall north  bleacher extension north

Ramp footings east  Equip Room slab north

Pool Fencing East  Pool Gutter North

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 6/30/15

Shade structure erection at all three sites is complete. Concrete slab on grade at Los Osos has been completed along with all CMU surrounds and joint sealants. Concrete slab on grade at Colony High School has been completed. CMU surrounds started at Colony High School. Rebar work for slab on grade at Montclair High School currently in progress.

Shade Structure 1 June Shade Structure 2 June

MONTCLAIR HIGH SCHOOL PROJECT PROGRESS THROUGH 5/31/15

Pool Improvements:

Underground pool plumbing and electrical is complete.  Underground storm drain is ongoing.  Roofing has started.  Balance of retaining walls is ongoing.  Bleacher extension is ongoing.  Phase 2 demo/grading/site work has started.  New pool supply building/rooms are ongoing.

Pool plumbing norht  Equipment room

North stair wall  Deck drain

bleacher extension  pump pit

equipment rooms south  Pool East

Press box and Bleacher Addition:

All items complete less punchlist and state elevator inspection.  The added window shutters are installed.

elevator flooring  snack bar

elevator landing  speakers on light poles

window shutters

HVAC Upgrades in Auditorium and Cafeteria:

The project started on May 22, 2015 upon completion of school.  The demo of the existing units is complete.  Exploratory demolition is being coordinated at the Auditorium and demotion of the ceiling in cafeteria has commenced.

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 7/31/15

Shade structure erection at all three sites has been completed. Slab on grade concrete work at all three sites completed. LOHS remaining activities are parking lot striping & truncated domes. New structures at LOHS have been ordered. CHS remaining activities are CMU surrounds, parking lot striping/truncated domes. MHS remaining activities are CMU surrounds, parking lot striping, truncated & traffic domes, new irrigation at quad and sod.

Montclair HS Shade 1 July Montclair HS Shade 2 July

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 5/31/15

Shade structure erection at Colony & Los Osos High Schools have been completed. Concrete slab on grade at Los Osos has been completed along with all CMU surrounds and joint sealants. Rebar work for slab on grade at Colony High School currently in progress. Shade structure erection at MHS is currently on-going along with CCD#2 addition of seat walls & revisions for ensuring maximum 2% ADA slope.

shade structure May 1 shade structure May 2

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 4/30/15

All foundations for all shade structures have been completed. Erection of shade structures have begun at all three sites, and are currently in progress. Seat wall excavation has begun at Montclair High School.

Montclair Shade Structure 1 Montclair Shade Structure 2

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS AND PRESS BOX & BLEACHER ADDITION PROJECT PROGRESS REPORT THROUGH 4/30/15

The project consists of the demolition and replacement of the swimming pool and associated pool equipment. New bleacher seating is also being added to the pool equipment building.

New pump pit walls have been poured and are backfilled. New CMU structures are built and embeds are set. Pool surge pit is complete. Underground pool plumbing is complete. Ceramic tile inside pool is complete. Footing for east retaining wall are complete.

Press box: Tie in electrical for press box and commence electrical for elevator. Complete bleachers and press box perimeter, ramps and stairs. Begin siding for the elevator and begin fire alarm tie in.

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS PROJECT

Pool looking east  east retaining wall

surge pit  surge pit north

retaining wall looking north  North pool plumbing

Pool looking west  New building

North Bleacher walls

MONTCLAIR HIGH SCHOOL PRESS BOX AND BLEACHER ADDITION PROJECTelevator siding  press box fencing

screen wall cmu  elevator facade

 

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS AND PRESS BOX & BLEACHER ADDITION PROJECT PROGRESS REPORT THROUGH 3/31/15

The Pool: New pump pit is excavated. New building, ramps & stair footings are complete. Footing for east retaining wall is complete. Pool surge pit excavation has started. Shotcrete for pool bottom, walls & lower gutter is complete. Gutter forming is ongoing. Ceramic tile at water line has started.

The Press box: Set the press box and elevator this month. Continue to work on the bleacher installation. The project completed the seating at the bleachers and commenced railings and stairs. Completed the ADA upgrades in restrooms and pulled primary and secondary electrical this month.

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS PROJECT

Pool looking east  Shallow Pool north

Deep pool east  Shallo Pool South

Deep pool SE  Pool SW

Surge Pit North  New Building North

 

MONTCLAIR HIGH SCHOOL PRESS BOX AND BLEACHER ADDITION PROJECT

bleacher delivery  Structural Steel

Elevator Hole  Bleacher installation

Press Box set  Elevator Delivered

Elevator Set  Press Box Conduit

 

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS AND PRESS BOX & BLEACHER ADDITION PROJECT PROGRESS REPORT THROUGH 2/28/15

The project consists of the demolition and replacement of the swimming pool and associated pool equipment. New bleacher seating is also being added to the pool equipment building.

The pool bottom reinforcement is complete. Pool plumbing piping is complete. Underground electrical is complete. Musco poles and lights are on-site.

Press box and Bleacher Addition had the structural steel delivered for the bleachers. All the landings and concrete ramps and asphalt required for the bleacher tie was completed. The ADA upgrades to the restrooms were completed. The new screen wall is complete.

Present:

  • Finish underground utilities
  • Pool reinforcing
  • Pool plumbing

Press box

  • Set structural steel for bleachers
  • Set press box
  • Set elevator

Future:

  • Pour backwash pit
  • New building footings
  • East side retaining wall

Press box

  • Set seating for bleacher
  • Commence electrical for press box
  • Complete elevator install

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS PROJECT

Pool East  Deep Pool SW

Shallow Pool South  Underground Elect N

MONTCLAIR HIGH SCHOOL PRESS BOX AND BLEACHER ADDITION PROJECT

Bleacher Footings  Slurry Electrical Trenches

Asphalt Placement  Restroom Screenwall

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS AND PRESS BOX & BLEACHER ADDITION PROJECT PROGRESS REPORT THROUGH 1/31/15

Pool Phase 1 demolition is complete. The pool contractor is on-site and is currently shaping the pool and installing pool gutter forms. The plumber and electrician have started underground utilities in the pool equipment room as well as the pool deck. The concrete contractor has started the retaining wall footing on the east end of the site.

The press box and bleacher addition has critical procurement of the bleacher material complete and ready to ship. The placement of footing rebar is complete at the bleacher and elevator footing. The concrete placement of the elevator pit walls is complete. The ADA upgrades in the bathrooms have commenced. The electrical rough in for the press box and elevator is in progress.

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS PROJECT

 

Pool SE  Pool NE

Pool NW  Pool Building South

MHS Press Box & Bleacher Addition Project

Underground Electrical  Excavated Press Box footing

Form elevator pit walls  Elevator Pit Walls Poured

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS AND PRESS BOX & BLEACHER ADDITION PROJECT PROGRESS REPORT THROUGH 12/31/14

The pool project consists of the demolition and replacement of the swimming pool and associated pool equipment. New bleacher seating is also being added to the pool equipment building.

The pool demolition contractor mobilized and set up construction entrance. Temporary fencing was installed. Existing pools, pool equipment and pool deck concrete has all been demolished. Pool equipment building slab concrete demolishing is ongoing. Excavation and re-compaction for the new pool is currently underway.

The press box and bleacher addition project consists of the demolition of the existing press box and replacing it with a new press box with an elevator and approximately 1,000 additional bleacher seats and associated ADA upgrades for path of travel.

The press box had the required demolition completed to excavate and re-compact for the bleacher and elevator footings.

MONTCLAIR HIGH SCHOOL SWIMMING POOL IMPROVEMENTS PROJECT

Pool Demo NE  Pool Demo NW

Pool Demo N  Pool Building Demo N

Pool Demo NE2

MHS Press Box & Bleacher Add. Project

Asphalt Demo SE  Stockpile at bleacher

Over Excavation  Bleacher pad