LOS OSOS HIGH SCHOOL PROJECT PROGRESS THROUGH 03/31/16

In the month of March the work consisted of the completion of the parking lot improvements with the remaining asphalt corrections at the drive entrance. In addition the remaining perimeter fencing and gates was completed. Also the completion of the bleachers was completed. The remaining work will be concrete at the east side at the location of the three storage containers which will be completed in the beginning of April.

West bleacher East  West Bleacher

Visitor Bleacher  East slope

East slope fencing  Asphalt Patch

LOS OSOS HIGH SCHOOL PROJECT PROGRESS THROUGH 02/29/16

In the month of February  the work consisted of the completion of the completion of the remaining concrete at the walkway in front of the north bleachers and the concrete at the east side of the bleacher. In addition the steel and aluminum for the bleachers was delivered in the middle of the month and the installation of the bleacher framing has started and completed on the east and west side bleachers. Also the aluminum decking and ramps have begun installation towards the end of the month.

walkway replacement  East concrete

Bleacher steel  Bleacher installation

B leacher decking

LOS OSOS HIGH SCHOOL PROJECT PROGRESS THROUGH 01/31/16

In the month of January the work consisted of the completion of the sidewalk and ADA compliance improvements to the sidewalks, pedestrian approaches, gates, hardware and handrails. In addition the east and west bleacher slopes were excavated for the bleacher footings and the footings and piers were poured and the power reroute for the Musco lighting pole was completed. After completion of the bleacher footings poured the slopes were graded and prepared for the concrete to be poured on the slope. The slope was poured at the end of the month.

Parking lot ADA  bleacher footing excavation

Bleacher footings and piers  east and west slope

bleacher slopes

LOS OSOS HIGH SCHOOL PROJECT PROGRESS THROUGH 12/31/15

Bleacher Addition

The parking lot ADA improvements at the walkways, ramps, approaches and hand rails are progressing.The bleacher additions at the east and west ends of the north bleachers  have cleared the slopes of vegetation and any debris and the excess soil removed. In addition, the footing excavation has begun this month.

Shade Structures:

In December, the shade structure frames were completed and the slab on grade was poured and the roof panels were installed.  The column wraps were completed and the fine grading is in progress.

Bleacher Demo  ADA improvements

ADA improvements East  ADA South

Footing excavation  Form Work

Feathering out grade

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 7/31/15

Shade structure erection at all three sites has been completed. Slab on grade concrete work at all three sites completed. LOHS remaining activities are parking lot striping & truncated domes. New structures at LOHS have been ordered. CHS remaining activities are CMU surrounds, parking lot striping/truncated domes. MHS remaining activities are CMU surrounds, parking lot striping, truncated & traffic domes, new irrigation at quad and sod.

Shade Structure 1 July Shade Structure 2 July

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 6/30/15

Shade structure erection at all three sites is complete. Concrete slab on grade at Los Osos has been completed along with all CMU surrounds and joint sealants. Concrete slab on grade at Colony High School has been completed. CMU surrounds started at Colony High School. Rebar work for slab on grade at Montclair High School currently in progress.

Shade Structure 1 June Shade Structure 2 June

DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 5/31/15

Shade structure erection at Colony & Los Osos High Schools have been completed. Concrete slab on grade at Los Osos has been completed along with all CMU surrounds and joint sealants. Rebar work for slab on grade at Colony High School currently in progress. Shade structure erection at MHS is currently on-going along with CCD#2 addition of seat walls & revisions for ensuring maximum 2% ADA slope.

Los Osos Shade Structure May 1 Los Osos Shade Structure May 2

 DISTRICT WIDE SHADE STRUCTURES PROJECT PROGRESS REPORT THROUGH 4/30/15

All foundations for all shade structures have been completed. Erection of shade structures have begun at all three sites, and are currently in progress.

Los Osos Shade Structure 2 Los Osos Shade Structure 1