Slide background
Chaffey High School GWS Auditorium Modernization

CHAFFEY HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 09/30/17

Interior demolition is continuing the basement level is complete and the auditorium ceiling was completed this month.  Work is progressing on the interior with work on removing the lobby ceiling and abatement is staying ahead of the demolition.  The exterior demolition closer to the building has commenced with walkways and ramps.  Shoring at the northwest corner for the new elevator is ongoing.

  

  

CHAFFEY HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 08/31/17

Exterior demolition is complete until exterior flat work starts back up next spring.  Interior demolition and abatement is ongoing on numerous floors.  Ceiling mural documentation is complete.  Auditorium ceiling demolition has started.

  

  

CHAFFEY HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 07/31/17

Exterior demolition is ongoing.  Main exterior utility installations are complete, this includes the Edison relocation of an existing panel to accommodate new stair tower.  Walkway patching is ongoing.  Auditorium interior scaffolding is complete.  Interior demolition and abatement is ongoing with the basement level completed this month.  Ceiling mural verification and pictorial documentation is ongoing.

  

  

  

CHAFFEY HIGH SCHOOL PROJECT PROGRESS REPORT THROUGH 06/30/17

Exterior demolition has started along with underground utilities.  Interior demolition and abatement has also commenced and the auditorium seating removal is complete.  The interior scaffolding is progressing in auditorium.