Etiwanda High School Auditorium

ETIWANDA HIGH SCHOOL PROJECT PROGRESS THROUGH 08/31/17

Underground building electrical and plumbing has been installed.  The building footing excavation for building B, D & C has started.  The site signal undergound is 75% complete.  The site sewer north of building B is complete.  The site fire line and storm drain south of building D is complete.  Footing excavation at building B has begun and rebar is being installed in the footing.

  

  

  

ETIWANDA HIGH SCHOOL PROJECT PROGRESS THROUGH 07/31/17

The underground domestic water, fire service and gas have been re-routed and tied back into the existing lines. The over excavation activity has started and will be completed by the end of the month.  Pad certification is complete and electrician and plumbing contractors are preparing to start the building underground early August.

  

  

  

 

ETIWANDA HIGH SCHOOL PROJECT PROGRESS THROUGH 06/30/17

Construction management team mobilized and set up construction fence.  Contracts were board approved on 6/13/17.  Demolition began and vegetation was removed.  Underground water and gas are being re-routed from under the new building.